CONSTRUCTION OF THE NEW ‘RAL’ HOUSE
Day by day progress
Below are a series of photos taken
from (almost) the same spot on the site at regular intervals to allow progress
to be tracked over the construction period

Before construction started

During clearing

Pegging out the house

4th October
Initial stumps are in place

6th October
All the stumps are in place

14th October
Stumps have been concreted and the
bearers are going in

19th October
Joists are starting to go in

28th October
Floor and Deck complete

30th October
First arch goes up
(no this
one is not from same spot as the others)

31st October
4 way
intercept in progress

1st November
4 way intercept complete

2nd November
End wall windows added

6th November
Start of 3 way intercept

7th November
3 way intercept complete

10th November
Frame complete

23rd November
Although this was taken 13 days
later it only took 4 days to put the tin on.

23rd December
Most changes in the past month have
been inside. The internal walls and doors have been fitted and plastered, the
shed mostly finished, and additional plumbing done.

18th April 2007
There have been many changes since
the previous photograph. Most obvious is the addition of some paint (the window
frames are next). The front ‘garden’ has been rotary hoed and
prepared for grass seed.