CONSTRUCTION OF THE NEW ‘RAL’ HOUSE

Day by day progress

 

Below are a series of photos taken from (almost) the same spot on the site at regular intervals to allow progress to be tracked over the construction period

 

 

Before construction started

 

 

During clearing

 

 

Pegging out the house

 

4th October

Initial stumps are in place

 

6th October

All the stumps are in place

 

14th October

Stumps have been concreted and the bearers are going in

 

19th October

Joists are starting to go in

 

28th October

Floor and Deck complete

 

30th October

First arch goes up

(no this one is not from same spot as the others)

 

31st October

4 way intercept in progress

 

1st November

4 way intercept complete

 

2nd November

End wall windows added

 

6th November

Start of 3 way intercept

 

7th November

3 way intercept complete

 

10th November

Frame complete

 

23rd November

Although this was taken 13 days later it only took 4 days to put the tin on.

 

23rd December

Most changes in the past month have been inside. The internal walls and doors have been fitted and plastered, the shed mostly finished, and additional plumbing done.

 

18th April 2007

There have been many changes since the previous photograph. Most obvious is the addition of some paint (the window frames are next). The front ‘garden’ has been rotary hoed and prepared for grass seed.

 